Universal Playground Repairs Scheduled

Thursday, September 13 2012 12:00 AM

Repair work to the Universal Playground is expected to begin on Wednesday, September 19th with the pressure washing of the tile.  The playground area will be closed through the 21st while this work is being done. 

The tile will then need to dry for a week, however the playground can be open during this time.  On September 28th crews will begin removing the tile that is glued down on the edges and any tile that is around a pole within the first 10 feet of the outer edge.   The playground can be open over the weekend but certain areas will be restricted.   These tiles will need to be removed prior to the machine arriving to begin compressing the tiles.

On Monday October 1st the playground will be closed for approximately three to five days while the tile is being replaced.  The area will be roped off.

As soon as work is complete the playground will be reopened. 