Bituminous Street Overlay Project Update

Friday, July 26 2013 12:00 AM

Work continues on the construction of bituminous milling, bituminous reclamation, bituminous pavement overlay and other appurtenant construction on several streets and parking lots in Red Wing.  These streets will have flaggers, lane closures in both directions, and traffic interruptions at various stages of construction.

A more detailed schedule for the week of July 15th is as follows:

  • Bituminous Milling Operations were completed on July 6th.  Adjustment of manhole structures, valve box structures and cleanup of milled streets has also been completed.
  • Bituminous Materials on Proposed Streets - Monarch delayed overlaying proposed streets earlier due to weather, however will be performing overlay operations of these streets on Friday, July 26th, Saturday, 27th, and Monday, July 29th (weather permitting).  Cleanup will follow directly after bituminous overlay operations have been completed on the street.  Proposed streets include:
Spruce Drive (Foursome to West Maple)
Maple Street (West Avenue to Southwood)
Foursome Street (Spruce to dead end)
Teeup Lane (Spruce to dead end)
Hi Park Avenue (Hennings to Cherry)
Birchwood Drive (West Maple to Poplar)
Willow Drive (West Maple to Red Oak)
Poplar Drive (West Maple to Birchwood)
Red Oak Avenue (Spruce to Poplar)
Forest Lane (Carol Lane to Helen)
North Park Street (West 6th to West 7th)
Helen Lane (Carol Lane to Forest)
Wallace Lane (Carol Lane to dead end)
Brooks Avenue (Pine Ridge to 500' south of Patch Cresent)
Chickadee Court (Pine Ridge to dead end)
East Avenue (12th to Oakwood Cemetery)
 

 

This project is scheduled to be completed before August 31, however is anticipated to be completed by August 2nd.  For Project updates, please visit the City of Red Wing's website at www.red-wing.org.  Motorists are encouraged to stay alert and drive carefully through the various construction zones.  The City of Red Wing appreciates drivers' cooperation and patience during this time of inconvenience.

Contact:  Alan Holm, Project Coordinator
Engineering Department
651-385-3624