Work began on the construction of bituminous milling, bituminous reclamation, bituminous pavement overlay and other appurtenant construction on several streets and parking lots in Red Wing.  These streets will have flaggers, lane closures in both directions, and traffic interruptions at various stages of construction.  

A more detailed schedule for the week of June 24th is as follows:

Monday, June 24th
Set up Traffic Control Equipment & Signage


Tuesday, June 25th
Milling & Reclamation of Bituminous Materials - Eunice Avenue, Potter Street Parking Lot, Public Works Parking Lot
Test Roll  Eunice Avenue to identify areas to excavate 


Wednesday, June 26th
Milling & Reclamation of Bituminous Materials - Public Works Parking Lot & Red Fox Drive
Subgrade Excavation - Eunice Avenue


Thursday, June 27th
Milling & Reclamation of Bituminous Materials - Red Fox Drive & Westwood Hills Drive
Subgrade Excavation - Eunice  Avenue


Friday, June 28th
Milling & Reclamation of Bituminous Materials - Westwood Hills Drive
Start Salvage Reclamation Item - Eunice Avenue & Potter Street Parking Lot


Saturday, June 29th
Salvage Reclamation - Potter Street Parking Lot & Public Works Parking Lot
(Saturday work dependant on weather and work load)


This project is scheduled to be completed before August 31.  For Project updates, please visit the City of Red Wing's website at  Motorists are encouraged to stay alert and drive carefully through the various construction zones.  The City of Red Wing appreciates drivers' cooperation and patience during this time of inconvenience.


Contact:  Alan Holm, Project Coordinator
Engineering Department