BITUMINOUS STREET OVERLAY CONSTRUCTION TO BEGIN JUNE 18, 2012

Thursday, June 14 2012 12:00 AM

Beginning June 18, 2012, Monarch Paving Company of Turtle Lake, Wisconsin will begin the construction of bituminous milling, bituminous reclamation, bituminous pavement overlay, bituminous pavement, and other appurtenant construction on several streets & parking lots in Red Wing starting on Bush Street (end of curb & gutter to Mississippi National Golf Links Parking Lot). These streets will have flaggers, lane closures in both directions, and traffic interruptions at various stages of construction. This project, when completed, will provide an improved driving surface for the public. The effected streets are as follows:

• SPRING CREEK AVENUE NORTH - Highway 61 West north to Lake Street
• MARTHA LANE
• KOSEC DRIVE - Graves Drive to dead end
• GRAVES DRIVE - Kosec Drive to Spring Creek Road South
• WEST END AVENUE
• WEST 6TH STREET - Washington Street to Minnesota Street
• WEST 7TH STREET - Featherstone Road to Buchanan Street
• SIEWERT STREET - Neal Street to Woodland Drive
• MALMQUIST AVENUE
• SPATES AVENUE - Hickory Street to Ash Street
• ASH STREET
• FOX FARM ROAD
• CHARLSON DRIVE
• OAKWOOD CEMETERY ROADS
• BLUFF STREET - 7th Street to 8th Street
• BUSH STREET - End of curb & gutter to Mississippi National Golf Links Parking Lot
• AP ANDERSON PARK - Road and Parking Lots
• ATHLETIC FIELD PARKING LOT

This project is scheduled to be completed before September 7. Motorists are encouraged to stay alert and drive carefully through the various construction zones listed. The City of Red Wing appreciates drivers' cooperation and patience during this time of inconvenience.

Contact: Alan Holm, Project Coordinator
Engineering Department
651.385.3624